The GMAT team is making a full QA sweep through the system in preparation for R2013a, our first non-beta release. For policies and procedures for this effort, see R2013a End Game QA Processes.

Schedule

Spec/test complete: November 30, 2012
Doc/wrap-up complete: January 31, 2013

Status Checklists

Use the following tables to track progress.

The feature name is linked to the spec for that feature. There's also a Google Collection (external link) with all listed feature specs in it for easy access to everything.

Some old feature specs are located in a GMAT Software Specification (external link) document, and have not yet been moved to their own individual documents.

 

Basic Dynamics/Models

Team: SPH, WCS, SJH

 

Powered Flight

Team: DSC, DJC, SJH

 

Solver Infrastructure

Team: DSC, DJC, SJH

 

Programming Infrastructure

Team: JJKP, WCS, SJH

 

Output/Utils

Team: RHQ, LOJ, SJH

 

Application Control

Team: Various Owners

NameIssueFeature Spec1System testsGUI testsReference docsWrap-up2
FRAC-11 Command-Line Interface (external link) [JJKP, WCS] XXN/AXX
FRAC-12 Startup File (external link) [JJKP, LOJ] XXN/AXX
Mission Tree (external link) [TGG] XN/AWaiting on bugsXX
FRAC-3 Script Editor (external link) [JJKP, TGG]GMT-2646 (external link)XN/AXXX
Output Tree (external link) [JMB] XN/A XX
Toolbar/Menu Bar (external link) [JMB] XN/AXM 
FRAC-8 Command Summary (external link)GMT-2652 (external link)XN/AXXX
FRAC-6 Resource Tree (external link) [SJH]XXN/AXXX

 

At Risk

Team: Various Owners

NameIssueFeature Spec1System testsGUI testsReference docsWrap-up2
C Interface* [JJKP]   N/A  
CallGMATFunction* [SPH]      
Event Locator* [JJKP]      
Global* [SPH]      
GMATFunction* [SPH]      
MATLAB Server* [SPH]      
Orbit Designer* [DSC]  N/A   
Save Command* [DSC]      
Socket Interface* [SPH]      




At risk: Event Locator, Orbit Designer, Ground Station, Formations, GMAT Function, CallGMATFunction, Socket Interface, Matlab server interface, Global
PrepareMissionSequence, Save


1The feature spec is a working document that contains draft text and metrics for the following areas:

  1. Baseline status report (feature audit)
  2. Requirements
  3. Functional spec
  4. Field/UI spec
  5. Test procedures


2Wrap-up consists of the steps outlined in the Wrap-Up section (external link) of the R2013a End Game QA Processes page.