Schedule

Spec/test complete: November 30, 2012
Doc/wrap-up complete: January 31, 2013

Status Checklists

Use the following tables to track progress.

The feature name is linked to the spec for that feature. There's also a Google Collection

with all listed feature specs in it for easy access to everything.

Some old feature specs are located in a GMAT Software Specification

document, and have not yet been moved to their own individual documents.

 

Basic Dynamics/Models

Team: SPH, WCS, SJH

 

Powered Flight

Team: DSC, DJC, SJH

 

Solver Infrastructure

Team: DSC, DJC, SJH

 

Programming Infrastructure

Team: JJKP, WCS, SJH

Name

Issue

Feature Spec1

System tests

GUI tests

Reference docs

Wrap-up2

FRR-32 Variable

GMT-2594

X

X

X

X

X

FRR-33 Array

GMT-2595

X

X