This page is used to track the process and progress of the R2013a R2014a release.

Table of contents

Table of Contents

 

Info

Target Date: August 14May 7, 20132014

Tasks

Info

All dates are referenced to 12:00 noon EDT.

For example, a deadline of March 15 should be interpreted as March 15, 12:00 noon EDT.

Early Tasks

These are long-lead early tasks that can be completed before the detailed release cycle.

Use "(/)" for the checkmark ((tick)) and "(x)" for the cross ((error))

N/A
TaskWhoStatus

Internal

Status

Notes

Review Previous Build Release R2013a Process Notes

All (tick)(error)(tick)(error) 
Get updated legal statement/licenseSPHN/A(error)(error)Needed by Code Freeze.
Update sample scripts
SPH(error)(tick)(error)

Needed by App Freeze.

  • Write examples that demonstrate new functionality
  • Clean up all errors and warnings
  • Remove deprecated fields
Write draft Release NotesJJKP(tick)(error)(tick)(error)

Needed by App Freeze.

See Writing Release Notes

Update standard descriptive textSPHN/AN/A(error)(error)

Needed by App Freeze.

Will be used in User Guide, websites, release announcement.

 

Update info on public-facing websitesJJKPN/A(error)N/A

Needed by Release Day.

See the list of sites. Update this list as well, if necessary.

Updated major sites before announcement. Minor ones can be updated a bit later.

Update release announcement contactsSPH(error)N/A

Needed by Release Day. Located here.

Put in order for additional iconsSPH(tick)(error)(tick)(error)

(if necessary)

Needed by Visual Freeze.

For QA Complete (August 1)

...