Info |
---|
Target Date: May 14, 2014 |
Tasks
Info |
---|
All dates are referenced to 12:00 noon EDT. For example, a deadline of March 15 should be interpreted as March 15, 12:00 noon EDT. |
Early Tasks
These are long-lead early tasks that can be completed before the detailed release cycle.
Use "(/)
" for the checkmark () and "(x)" for the cross ()
Task | Who | Status | Internal Status | Notes |
---|---|---|---|---|
Review Previous Build Release R2013b Process Notes | All | |||
Get updated legal statement/license | SPH |
| Needed by Code Freeze. | |
Update sample scripts | SPH |
| Needed by App Freeze.
| |
Write draft Release Notes |
SPH |
| Needed by App Freeze. | |
Update standard descriptive text | SPH | Needed by App Freeze. Will be used in User Guide, websites, release announcement. | ||
Update version number on User Guide cover page | JJKP | Needed by App Freeze. Contact Katy Gammage or Mary Hrybyk-Keith. Next time: integrate sejda-console to do this automatically. | ||
Update info on public-facing websites | JJKP | N/A | Needed by Release Day. See the list of sites. Update this list as well, if necessary. Updated major sites before announcement. Minor ones can be updated a bit later. | |
Update release announcement contacts | SPH | N/A | N/A | Needed by Release Day. Located here. |
Put in order for additional icons | SPH | N/A | N/A | (if necessary) Needed by Visual Freeze. |
For QA Complete (April 21)
...